MABA Suitez: what changed between the groundbreaking and the sales kit
News at the November 2025 groundbreaking said about 1,300 units, 60 storeys and 2031. The November 2026 sales kit says something different.
Published Checked 2 min read
If you search for MABA Suitez, you will find two sets of figures. One comes from news of the groundbreaking in November 2025. The other comes from the developer's sales papers a year later.
Here they are side by side, with their dates and sources. We do not know why they changed, so we will not guess.
What did the news say in November 2025?
EdgeProp reported on the groundbreaking with a Kuala Lumpur dateline of 30 Nov 2025. Its web page shows 1 Dec 2025.
- Units: about 1,300, made up of serviced apartments.
- Height: a 60-storey serviced apartment project with two towers.
- Completion: expected in 2031.
What do the newer sales papers say?
The agent sales kit is dated 6 Nov 2026. The agent sales summary was updated on 11 Nov 2026.
- Units: 914 in all, with 534 in Tower A and 380 in Tower B.
- Height: two towers, Tower A with 54 storeys and Tower B with 50 storeys.
- Completion: 52 months after the APDL, says the summary. 60 months after the APDL, says the kit.
Why does the finish date matter?
The APDL is the developer's licence and advertising and sales permit. As of November 2026, the papers say there is no APDL yet and the launch date is still to be confirmed.
So the newer papers do not give a finish year. They count the months from a date that has not happened yet. Four to five years from the APDL is the best reading today.
Which figures do we use?
Our review uses the figures in the newer sales papers.
If you see 1,300 units or 60 storeys on another site, it may be quoting the 2025 news. Ask the agent for the official figures in writing before you decide anything.
Sources
Checked 27 Nov 2026. Official means a law, a ministry or a regulator. News means a news report.
- NewsEdgeProp, report on the Exsim Development and MABA groundbreaking, dateline 30 Nov 2025, page dated 1 Dec 2025 (opens a new tab)
Opened in full on 27 Nov 2026. About 1,300 units; 60-storey serviced apartment comprising two towers; expected completion 2031.
- Both SidesBoth Sides, MABA Suitez review (opens a new tab)
From the sales kit (6 Nov 2026) and sales summary (11 Nov 2026): 914 units (534 and 380), towers of 54 and 50 storeys, keys 52 to 60 months after the APDL, no APDL and no launch date yet.
- Both SidesBoth Sides, MABA Suitez legal and sources (opens a new tab)
Dates of the sales kit and sales summary; APDL not issued yet.